Final Touches Before Paving Mono And Greenley Intersection

Sponsored by:

Sonora, CA — Work will continue during the overnight hours only this week on the Mono Way and Greenley Road widening project.

The construction hours will be 7pm through 7am, today through Friday. Work this week will consist of final preparations ahead of paving, which will be November 5-7, and final striping, November 13-16. This week’s work will include removing the thermoplastic pavement striping and finalizing the patching/crack sealing. Be prepared for 10 minute traffic delays this week if traveling through the intersection during the overnight work hours.

  • Mono Way and Greenley Road Intersection